Campus Wired Network Replacement

Overview

As announced in April 2021, Information Services will be replacing the University of Richmond campus wired network this summer, beginning Monday, May 24. All work is expected to be completed by August 12th.

Each network installation will be associated with a total, wired and wireless, network outage in the building(s) scheduled for that day.

Please address all questions and concerns regarding the schedule to sysnetpmo@richmond.edu

Note that the remote access VPN will continue to be available throughout the install period, as a potential alternative to utilizing the on campus network. Additional information on the VPN is available at What is the VPN?

Details / Instructions

Building Name Network Outage Date
Atlantic House 5/24/21
Dennis Hall  5/24/21
Law Dormitory 5/24/21
Marsh Hall 5/24/21
Gateway Village 151 5/25/21
Gateway Village 153 5/25/21
Gateway Village 155 5/25/21
Gateway Village 157 5/25/21
Gray Court 5/26/21
Lakeview 5/26/21
Moore Hall 5/26/21
Pacific House 5/26/21
Robins Hall 5/27/21
South Court 5/27/21
UFA 160 5/27/21
UFA 162 5/27/21
UFA 164 5/27/21
UFA 166 5/27/21
UFA 191 5/27/21
UFA 193 5/27/21
UFA 470 5/27/21
Chapel 6/1/21
Crenshaw Field 6/1/21
Print Shop 6/1/21
Westhampton Residence Hall 6/1/21
Wilton Center 6/1/21
Wood Hall 6/1/21
Westhampton Deanery 6/2/21
Heilman Dining Center 6/2/21
Thomas Hall 6/2/21
UFA 168  6/2/21
UFA 170 6/2/21
UFA 172 6/2/21
Student Activities Center  6/3/21  PM
Jepson Alumni Center 6/3/21
UFA 472 6/3/21
UFA 474 6/3/21
UFA 476  6/3/21
UFA 481 6/3/21
UFA 483 6/3/21
UFA 486 6/3/21
Physical Plant 6/4/21
Pitt Field 6/4/21
Special Programs 6/4/21
Steam Plant 6/4/21
Weinstein Hall 6/7/21  AM
Robins School of Business (excluding Queally Hall) 6/8/21
Robins School of Business (Queally Hall) 6/9/21
Jeter Hall 6/9/21
Sarah Brunet Hall 6/9/21
Robins Center (Weinstein Center for Recreation & Milhiser Hall) 6/10/21
Puryear Hall 6/11/21
Spider Mgmt 6/11/21
Tyler Haynes Commons 6/11/21
Lora Robins Court 6/14/21
Modlin Center 6/14/21
Boatwright Memorial Library ( Admin Wing) 6/15/21
Boatwright Memorial Library (Main Library) 6/16/21
Lora Robins Trailers 6/17/21
Richmond Tennis Court Trailers 6/17/21
Visual Arts Building (includes Keller) 6/17/21
Well Being Center & Queally Athl Ctr 6/17/21
Law School (Library area & Offices) 6/21/21
Law School (Classrooms & Offices) 6/22/21
Robins Stadium 6/23/21
Maryland Hall 7/7/21
Richmond Hall 7/7/21
Ryland Hall 7/7/21
Whitehurst 7/7/21
Fine Arts Building (Booker Hall) 7/12/21
North Court 7/26/21
President’s House 7/26/21
Jepson Hall (ground floor) 7/27/21
Jepson Hall (1st floor) 7/27/21 - 7/28/21
Jepson Hall (2nd floor) 7/28/21
Freeman Hall 7/30/21
Queally Welcome Center 7/30/21
Gottwald Center for the Sciences 8/11/21
Carole Weinstein  International Center 8/12/21

See Also

Five-minute video summary of the network replacement and what you can expect from the new network.